Budgets & AFE

FY2026 · Obite Gas Plant · Opex maintenance

Budget vs actual
Cost centreCategoryBudgetCommitted (POs)Actual (WOs + invoices)RemainingUsed
OB-MECH-01 Spares ₦25.0m ₦18.4m ₦14.1m ₦6.6m
74%
OB-MECH-01 Labour & contractors ₦40.0m ₦22.0m ₦19.7m ₦18.0m
55%
OB-ELEC-01 Spares ₦12.0m ₦11.6m ₦9.2m ₦0.4m
97%
OB-INST-01 Calibration services ₦8.0m ₦3.1m ₦3.1m ₦4.9m
39%
OG-MECH-01 Spares ₦9.0m ₦4.4m ₦4.0m ₦4.6m
49%

Used is committed against budget. Remaining is budget less committed.

AFE-0093 · K-201 compressor overhaul

Awaiting approval
ItemEstimateCommittedActual
OEM overhaul kit₦2,400,000
Vendor field service (14 days)₦1,500,000
Crane hire₦300,000
Total₦4,200,000

Justification: MTBF fallen to 31 days; three unplanned trips since June. Linked WOs: WO-2044, WO-2038.

AFE approval chain

  • Maintenance Supervisor
  • Facility Manager
  • Cost Controller — you
  • Asset Manager — over ₦3m

Invoices to match

  • INV-8812 Sulzer · ₦1,690,000 · PO-0341 GRN
  • INV-8809 Flexitallic · ₦168,000 · PO-0339 GRN
  • INV-8801 Crane hire · ₦300,000 · no PO Hold

Three-way match: purchase order, goods receipt, invoice. A mismatch goes on hold.

Accounting export

Last export 31 Aug → SAP FI (journal batch 0826)

Pending lines 148 · ₦6.2m